Street Constuction Update

221216 - Street Phase 1 Logo
Residents, construction update on the City’s bond-funded Street Project. 


2.22.24
Residents, continued great progress by D&D contractors in the bond-funded Street Project. Bent Oak excavation started this week. Concrete curbs and driveways on Windmill started this week. First lift of asphalt goes down on 100 / 200 Blk Fawn Mon/Tues next week. Bent Oak road will be closed to thru traffic and D&D asks all residents have vehicles out of driveway by 8AM during excavation. Call D&D's Barry Bonn @ 210.371.6504 if you need assistance.

2.9.24
Residents, a tremendous week of progress by D&D contractors in the bond-funded Street Project. Shavano Dr got both first and final lifts of asphalt, along with 300 Blk of Fawn and Chimney Rock. All three roads are now complete with only cleanup, sod and grass remaining. Also this week 100 / 200 Blk of Fawn finished concrete curbs and driveways and Windmill was excavated. Next week concrete stabilization of Windmill will occur. D&D is still sorting out when asphalt will go down on 100/200 Blk of Fawn, but could be next week as well.

On Windmill, driveway access in and out will be limited during the concrete stabilization process. Road will be closed to thru traffic and D&D asks all residents have vehicles out of driveway by 8AM. Call D&D's Barry Bonn @ 210.371.6504 if you need assistance.

Concrete Curbs complete on 100 Blk Fawn
240222 - 100 Blk Fawn Curbing

Windmill Road Excavated
240222 - Windmill Excavated

Town Hall power point is available here.

The fastest way to receive news on the project is via texting at TextMyGov.

COSPROAD QRScan the QR Code or Text COSP ROAD to 91896 to sign up for project text alerts direct to your phone!

Text ROADS to 210.853.2003 at any point to notify staff of an issue during the construction project.



Map of Phase 1A Project Status
240220 - Street Project Ph1A Status Map