Street Constuction Update

221216 - Street Phase 1 Logo
Residents, construction update on the City’s bond-funded Street Project. 

 4.18.24

Residents, construction update on the Bond-funded street project. Bent Oak asphalt is complete. Phase 1 of Cliffside (N.W. Military to 128 Cliffside) is has ongoing concrete curbs and driveways work. Asphalt likely to be laid first week of May in Phase 1. Phase 2 of Cliffside (128 Cliffside to 400 Cliffside) started reconstruction this week. Late next week Phase 2 of Cliffside will get concrete subgrade stabilization. There will be times when access will be limited throughout the process of cement stabilization (limited to 4-6 hours). Phase 3 of Cliffside (400 Cliffside to 423 Cliffside) is likely to start reconstruction in early May. Call D&D's Barry Bonn @ 210.371.6504 if you need assistance.

4.4.24
Residents, D&D hit rock subgrade in first Phase of Cliffside, that combined with rain has slowed progress. Cliffside Phase 1 will not be concrete stabilized but curbs will be strengthened with dowels into the rock. Concrete curbing and driveways will begin next week. Bent Oak concrete work is complete. Asphalt to go down on Bent Oak on Monday and Tuesday next week. All this is pending weather as more rain is in forecast. Phase 2 of Cliffside (128 to 400 Cliffside) will start reconstruction within the next two weeks. TxDOT Tie-In coordination ongoing, construction to occur in next several weeks. Call D&D's Barry Bonn @ 210.371.6504 if you need assistance.

Cliffside will be done in three phases:
Phase 1 – N.W. Military to 128 Cliffside
Phase 2 – 128 Cliffside to 400 Cliffside (near Windmill)
Phase 3 – 400 Cliffside to 423 Cliffside (near the saddletree transition)


NW Military Tie-In with Windmill Road
240322 - NW Military Tie In Windmill

Cliffside Phase 1 with road excavated
240322 - Cliffside NW Mil-128 Excavated

Town Hall power point is available here.

The fastest way to receive news on the project is via texting at TextMyGov.

COSPROAD QRScan the QR Code or Text COSP ROAD to 91896 to sign up for project text alerts direct to your phone!

Text ROADS to 210.853.2003 at any point to notify staff of an issue during the construction project.



Map of Phase 1A Project Status
240418 - Street Project Ph1A Status Map